Quick answer
Under the General Insurance Code of Practice, insurers keep you updated at least every 20 business days and decide a claim within four months of receiving it, or within 12 months if exceptional circumstances apply. Business interruption claims usually finish last, because the loss can't be measured until trading recovers or the indemnity period ends. Plan cash flow for six to twelve months.
Key points
- Updates at least every 20 business days; a decision within four months in most cases
- Exceptional circumstances can stretch a decision to 12 months
- Business interruption money usually arrives after the costs it covers
- A redrafted Code went to public consultation in mid-2026; the current Code still applies
- Size any bridge on the amount the insurer is likely to pay, not the headline claim
A business insurance claim in Australia typically gets a decision within four months under the General Insurance Code of Practice, with progress updates at least every 20 business days. After a large catastrophe the decision can take up to 12 months. The business interruption part almost always settles last, so plan for six to twelve months between the damage and the final payment.
That plan matters more than the claim form. A fire, flood or storm creates two events: the costs that start the day after (clean-up, wages, rent, replacement stock) and the insurer’s payments that arrive in pieces over the following months. The span between them is what breaks businesses that were otherwise sound. This guide sets out the timetable the insurer works to, why the interruption claim trails everything else, and how to carry the gap without overloading the business.
What timeframes does the Code set for insurers?
Most general insurers in Australia subscribe to the General Insurance Code of Practice, which AFCA monitors and explains. The Moneysmart summary of claim steps is written for home insurance, but the same Code timeframes generally apply to small business policies:
- A first response within 10 business days of you lodging the claim.
- A progress update at least every 20 business days.
- A decision within four months of receiving the claim, unless exceptional circumstances apply.
- Up to 12 months where exceptional circumstances exist, such as a catastrophe affecting thousands of policyholders at once.
Read those as limits, not targets. Also note that a “decision” is not money in your account. Accepting a claim starts a second phase of quoting, authorising repairs and paying in stages.
Is the insurance Code changing?
It may be, but not quickly enough to affect a claim lodged this year. On 24 June 2026 the Insurance Council of Australia opened consultation on a redrafted Code, with submissions closing on 21 July 2026. The headline proposals:
- Enforceability. Subject to ASIC approval, most of the Code would become legally enforceable as part of the insurance contract for the first time.
- Automatic acceptance. Home and motor claims left undecided after 12 months would be treated as accepted, subject to exceptions.
- Cash settlements and points of contact would be strengthened.
Two caveats for business owners. The automatic-acceptance proposal is aimed at home and motor claims, not commercial property or interruption claims. And until a new Code is approved and its transition period ends, the current Code is the one your insurer is bound by. Plan on today’s rules.
What are the stages of a business claim?
A combined property damage and business interruption claim generally moves through these stages:
| Stage | What happens | Typical span |
|---|---|---|
| Notify | Claim lodged, claim number issued | Day 1 |
| Make-safe | Emergency works to stop further loss | Days to weeks |
| Assess | Loss adjuster inspects and reports | 2–6 weeks |
| Scope | Builders and suppliers quote, insurer reviews | 1–3 months |
| Decide | Insurer accepts, partly accepts or declines | Within 4 months (12 if exceptional) |
| Rebuild and restock | Repairs authorised or cash settled, often in stages | Months |
| Interruption loss | Lost profit measured over the indemnity period | Last to settle |
After a regional disaster, every span stretches: assessors, builders and materials are all in short supply at the same moment.
Why does the business interruption claim settle last?
Business interruption cover replaces lost gross profit and pays some extra costs of working while you recover, within the policy limits and indemnity period. To measure that loss, the insurer needs to compare what the business actually earned after the event with what it would have earned. That means:
- Two or more years of historical accounts, to set the trend.
- Monthly results after the event, which only exist once each month has passed.
- Evidence of increased costs, such as temporary premises, equipment hire or overtime.
- Often a forensic accountant working for the insurer, and sometimes one working for you.
The structural problem is simple: the payments meant to cover lost profit arrive after the bills that profit would have paid. Even a fully covered business runs a cash deficit through the recovery.
What slows claims down, and what can you control?
Missing information causes most delays. The levers within reach:
- Lodge on day one and quote the claim number on every document.
- Photograph and film everything before clean-up, and keep damaged stock until the assessor says otherwise.
- Keep every receipt for make-safe work, hire, temporary premises and replacement stock.
- Bring your accounts up to date. Interruption claims move faster when last year’s financials and current management accounts are ready.
- Answer requests within the week. Each slow round of questions can add a month.
- Keep a contact log with dates, names and what was agreed.
- Get help on complex claims. A broker or claims preparer can be worth their fee on a large interruption claim.
If handling becomes unreasonably slow, complain to the insurer in writing. If that fails, small businesses can escalate to the Australian Financial Complaints Authority, subject to its eligibility rules.
How do you fund the business while the claim runs?
Fixed costs don’t pause. Rent, loan repayments, wages for staff you want back, premiums and tax all continue while revenue has dropped or stopped. Most recoveries are funded from several sources at once:
- Progress payments. Ask what the insurer can pay now: make-safe costs, an agreed stock figure, or an early interruption instalment.
- Recovery grants. After declared disasters, governments regularly open grants for clean-up, repairs and reopening. Disaster Assist lists assistance by event and area, and business.gov.au keeps a page on business assistance for disasters and emergencies. Programs have closing dates, so check early, and read how each one treats costs your insurance will also cover.
- Supplier and landlord arrangements. Many will agree temporary terms if you ask before an invoice is overdue.
- ATO help. The ATO can often extend lodgement or payment timing for businesses affected by disasters.
- A bridge, with the claim payment as the exit.
When the insurer’s money is what will eventually put things right, a short bridge can keep staff and customers in place until it lands. You can ask how a claim bridge would work for you, and there’s no credit check when you first enquire.
How much of the claim can you count on?
Less than the headline figure. The amount paid can be reduced by:
- Excesses on each section of the policy.
- Under-insurance, where the sum insured is below the real loss (common after construction costs rose).
- Exclusions, such as flood definitions or gradual damage.
- Depreciation on some items, depending on the wording.
- Disputed items about cause, scope or the length of the indemnity period.
Plan on the amount you’re confident of, and expect any lender to do the same. Our page on bridging to an insurance payout explains how lenders discount a claim, and the bridging calculator lets you test what happens if the payout comes in lower or later.
A worked example
This is an illustrative scenario, not a client file.
A family-owned hardware store in a regional river town is flooded. The building needs major repairs, most stock is lost, and the store can’t trade for about four months. The policy covers building, contents and six months of business interruption. The owners hold the freehold.
| Month | Event |
|---|---|
| 0 | Claim lodged; clean-up starts; core staff kept on |
| 1 | Assessor’s report; stock loss partly agreed |
| 2 | Builder’s scope approved; first stock payment |
| 4 | Store reopens with a reduced range |
| 7–10 | Interruption claim settled in instalments |
They map the bridge against the exit:
| Line | Amount |
|---|---|
| Total claim estimate | $620k |
| Amount they’re confident of (after excesses and a disputed item) | $480k |
| Bridge drawn for restocking and wages (peak debt) | $260k |
| Estimated fees and interest over a 10-month term | –$35k |
| Insurance received by month 10 | $480k |
| End debt | $0 |
The bridge is secured over the building, sized at a little over half of the amount they were confident of, and reduced as each payment arrives. Because they planned for a ten-month term instead of four, the slow interruption settlement didn’t force an extension. If you’re weighing how long a facility should run, see our page on choosing a bridging loan term. If there’s no property to offer, an unsecured cash-flow bridge may suit a smaller gap where trading has continued, and our page on money you’re owed as the exit covers claims alongside refunds and grants.
What should you do in the first 30 days?
- Lodge the claim and record the claim number.
- Document all damage before anything is moved.
- Arrange make-safe work and keep every invoice.
- Ask for your assessor’s name and the next steps in writing.
- Gather two years of accounts and current management accounts.
- Check Disaster Assist and business.gov.au for any programs open in your area.
- Build a week-by-week cost plan for the next six to twelve months.
- Start any finance conversation early, while you still have options.
When the insurer’s clock runs slower than yours
The claim will move at the insurer’s pace. Wages, rent and suppliers move at yours. Closing that span is what we do every day, and we’d rather plan it with you in month one than in month five.
The enquiry takes about 60 seconds and there’s no credit check when you first enquire. We don’t send your details to a pile of lenders, so you won’t be fielding calls from strangers. A real person who understands claim gaps looks at your situation and calls you.
Please fill the form in accurately: the claim estimate, what has been paid so far, where the insurer is up to, and the security you can offer. Accurate figures let us size the bridge correctly from the start.
Ready when you are
Check your options in about 60 seconds
A few quick questions. Asking won't touch your credit file, your details aren't sent to a pile of lenders, and a real person reads every enquiry.
Frequently asked questions
How long does an insurer have to decide a business insurance claim?
Under the General Insurance Code of Practice, an insurer should decide a claim within four months of receiving it. Where exceptional circumstances apply, such as a major catastrophe, that can extend to 12 months. It must also update you on progress at least every 20 business days.
Why do business interruption claims take longer than property claims?
Because the loss keeps accruing until the business has recovered or the indemnity period ends. The insurer compares actual trading after the event with what the accounts suggest would have happened, and those figures only exist month by month.
Can I get an interim or progress payment?
Many insurers pay parts of a larger claim once they're agreed, such as make-safe costs, stock or an early business interruption instalment. Ask in writing what can be paid now and what evidence the insurer needs to release it.
Is the General Insurance Code of Practice changing?
The Insurance Council of Australia opened consultation on a redrafted Code in June 2026. It proposes making the Code legally enforceable as part of insurance contracts once ASIC approves it, and automatic acceptance of home and motor claims undecided after 12 months. Until a new Code commences, the current one applies.
What can I do if my claim is taking too long?
Complain to the insurer in writing first and keep a dated log of every contact. If the internal complaint doesn't resolve it, small businesses can take the dispute to the Australian Financial Complaints Authority, subject to its eligibility rules.
Is there government help after a natural disaster?
After declared disasters, recovery grants and other support are often offered for clean-up, repairs and reopening. Disaster Assist and business.gov.au list current programs by event and area, along with their closing dates.
Can I borrow while waiting for my insurance payout?
Yes. A bridging loan can fund repairs, restocking and wages, with the claim payment as the planned exit. It's usually secured over property, or for smaller gaps assessed on trading, and sized on what the insurer is likely to pay.
Sources
- Moneysmart — How to make a home insurance claim (General Insurance Code timeframes)
- AFCA — General Insurance Code of Practice
- AFCA — Making a complaint about a financial firm
- Insurance Council of Australia — Consultation on new Code of Practice (June 2026)
- business.gov.au — Business assistance for disasters and emergencies
- Disaster Assist